The plumbing system is completed. External plumbing work is in progress

18/10/2024

The plumbing system is completed. External plumbing work is in progress. Installation of sanitary in bathrooms is started.

Electricaland low-current wiring is complete, cabinet assembly work is underway. Preparation for the installation of sockets and switches in apartments is in process.

Tiling in the apartments is complete. Tiling in common areas is 70% complete.

Plastering work in apartments is 100% complete, corridors of residential floors - 100%, in the stairs and elevator halls - 15%. Painting works is in apartments and common corridors are in process.

Apartment entrance doors have been installed.

Elevatorshave been installed.

Installation of external and internal air conditioner units - 40% complete.

Installation of the aluminum facade structure on the staircase side is in process, readiness- 90%.

The facade on the boulevard side is complete. The installation of stone for fencing balconies has been completed on the southern and western facades, and stone has been installed on the terraces. Northern facade – 60% complete.

The sprinkler fire extinguishing system has been installed in the parking lot, and commissioning work is underway.

Installation of the ventilation and smoke removal system of the underground parking is inprocess.

Thermal insulation of the roof and terraces has been completed. Cement-sand screed hasbeen applied on the roof and terraces over the thermal insulation.