The facade on the east side of the building is finished, the scaffolding has been dismantled, work has begun on the 0th floor

4/4/2025

The facade on the east side of the building is finished, the scaffolding has been dismantled, work has begun on the 0th floor. Decorative grilles near the air conditioners have been installed, the glass fences of the balconies are under installation. The external units of the air conditioners of apartments type 8 have been fully installed. Roller shutters are being adjusted.

Painting of the corridors on 1-8 floors is finished, painting work is underway on the stairs and elevator halls. Electrical work in the entrance group has been completed.

Roof waterproofing is completely ready, waterproofing of the parking roof and driveways is being carried out. Doors to technical rooms and doors to the roof have been installed, installation of an active lightning rod (lightning protection) has been completed.

In the process of painting apartments of the type 8. Installation of plumbing equipment and installation and connection of mirrors is being completed. Installation of baseboards (2-8 floors) is being carried out, comments on the installation of doors are being corrected. The final preparation of apartments on floors 7-9 for handover is underway. The final cleaning of apartments on the 4th floor for handover to the owners has begun.