Stretch ceilings are under installation in bathrooms and apartments on the upper floors

14/12/2024

Stretch ceilings are under installation in bathrooms and apartments on the upper floors. Water meter cabinets have been installed on the floors.

Decorating elevator portals is underway.

Installation of fire doors continues, doors on 1-5 floors are completed.

Installation of aluminum structures in common corridors continues, floors 1-8 - completed.

Work is underway on the northern facade ofthe building: srteet plaster has been applied, installation of the drainage system and external air conditioner units continues.

Electrical work in the underground parkingis in progress. wall painting work is underway.

 