13/2/2024
Reinforced concrete works arecompletely finished, the parking ramp is done.
Brick works are 100% completed.
Plumbing has been completed on 1st-6th floors, works are in process on the 7th floor.
Electrical wiring is completed onthe 1st-5th residential floors, 30% ready on the 6th floor.
Low-current wiring is done on1st-2nd floors.
Fastenings for wrist units of airconditioners and laying of routs are under installation on the 8th floor.
Installation of windows - 35%
Plastering works are done on 1-4floors.
Waterproofing on balconies andterraces is done on the 1st-4th residential floors.