Reinforced concrete works are completely finished, the parking ramp is currently being filled

12/1/2024

Reinforced concrete works arecompletely finished, the parking ramp is currently being filled. Brick works are in process on the9th  floor - 80% completed.

Plumbing has been completed on 1st-5th floors, works are in process on the 6th floor. Electrical wiring is completed onthe 1st-4th residential floors, 90% ready on the 5th floor.

Fastenings for wrist units of airconditioners and laying of routs are under installation on the 7th floor. Installation of windows - 10%.

Plastering works are done on 1-2floors. Waterproofing on balconies and terraces is done on the 1st and 2nd residential floors.