12/1/2024
Reinforced concrete works arecompletely finished, the parking ramp is currently being filled. Brick works are in process on the9th floor - 80% completed.
Plumbing has been completed on 1st-5th floors, works are in process on the 6th floor. Electrical wiring is completed onthe 1st-4th residential floors, 90% ready on the 5th floor.
Fastenings for wrist units of airconditioners and laying of routs are under installation on the 7th floor. Installation of windows - 10%.
Plastering works are done on 1-2floors. Waterproofing on balconies and terraces is done on the 1st and 2nd residential floors.