Plumbing works have been completed from the 1st to the 10th floor, and work is currently underway on the -1st and 0th floors

27/5/2024

Plumbing works have been completed from the 1st to the 10th floor, and work is currently underway on the -1st and 0th floors.

Electricity is distributed from the 1st to the 10th floor inclusively, the weak point is on the 8th floor.

Waterproofing in the bathrooms is done on the 1st and 2nd floors.

Tilework is finishedin apartments on the 1st floor, work is underway on the 2nd.

Plastering works are carried out on the 9th floor.

The screed is made from the 1st to the 6th floor inclusively.

Waterproofing on the terraces is completed, preparations for waterproofing on the roof are underway.

On the balconies, the first layer of waterproofing on concrete is made.

Windows are installed from the 1st to the 10th floor.

The facade on the side of the boulevard - insulation is completed, preparations for plastering workare underway.