6/11/2023
Framework for floorslab between 9th and 10th floor іs being installed. Brickwork is fully completed on the 6th floor, on the 7th - 10% ready. Plumbing is ready on 1st-4th floors, works proceeded on the 5th floor. Electrical wiring is done onthe 1st-2nd floors and already has been started on the 3rd.